Projects

Completed Projects


List of Completed Projects under ISCL:

Sl. No. Project Implementing Agency Project Cost in Cr Financial Progress (in cr.) Remark
1 Kangla Nongpok Torban (Western River Front of Imphal River) Phase-I PDA 22.96 21.96 Inaugurated by PM in Jan 2022
2 Thangal Lambi (Development Mall Road) Phase –I’ MPHC 9.52 8.82 Inaugurated by PM in Jan 2022
3 Nongpok Thong MPHC 7.52 7.06 Inaugurated by HM in Jan 2023
4 App based Public Bicycle Sharing (100 Nos of cycle with 20 Nos docks) Yaana Technologies 3.09 1.27 Launched in Sep. 2022 by M/MAHUD
5 Re-sectioning of Imphal River (Development of Western River Front -I) WRD 1.76 1.76 Completed
6 Citizen Facilitation Center VFS 0.59 0.59 Completed
7 Supply, Erection and Fixing of 120/130 W LED Street Lamp along the eastern bank of Naga Nala MSPDCL 0.37 0.37 Completed
8 Redevelopment of Indira Park IMC 0.47 0.48 Completed
9 Supply, Commissioning of 11 kV Line (0.12 km), & of 1x100 kVA and 1x63 kVA Distribution Sub-station MSPDCL 0.17 0.17 Completed
10 Development of two-wheeler parking in the basement of Luxmi Market PWD (Building) 3.87 1.90 Completed
11 Kangla Battery Vehicle – 3 Nos 14-seater & 3 Nos 6-seater Kangla 0.48 0.48 Completed
12 Development of 500 TPD Capacity Legacy Waste Processing Plant at Lamdeng M/s Londan Dollar 16.18 6.54 Completed
13 Renovation of Drainage at Thangal Bazar MUDA 6.29 2.52 Completed
14 Construction of Security Kiosk & Toilet Block at Kangla Nongpok Torban Phase-I Oinam Oken Singh 0.50 0.50 Completed
15 Augmentation of Municipal Solid Waste Management GeM Portal 7.36 5.27 Completed
16 4 & 2-wheeler Parking at Ima Keithel 1 & 3 PWD (Building) 4.29 4.28 Completed
  Sub Total of A   85.42 63.97  